Central Ohio Timeline Guide
How Long Does a Home Remodel Take in Central Ohio?
Real schedules from projects in Hocking, Fairfield, and Franklin counties — from the first design meeting through final inspection, phase by phase.
Timelines by project type
| Project | On site | Start to finish |
|---|---|---|
| Hall / guest bathroom | 3–5 weeks | 8–12 weeks |
| Primary bath / spa build | 5–8 weeks | 11–16 weeks |
| Kitchen remodel | 6–10 weeks | 14–20 weeks |
| Finished basement | 6–10 weeks | 10–16 weeks |
| Deck or siding | 1–3 weeks | 4–8 weeks |
| Home addition | 4–7 months | 6–10 months |
| Custom natural rock pool | 8–16 weeks | 4–7 months |
"Start to finish" includes design, selections, permitting, and material lead times — the part most schedules leave out.
The eight phases of a Central Ohio remodel
01 Design & selections
2–5 weeksSite measure, scope, layout drawings, and every finish selected. Locking selections here is what keeps the build on schedule later.
02 Permitting & ordering
1–4 weeksPermit submittal to Columbus, Franklin, Fairfield, or Hocking County, and long-lead orders placed — cabinets, windows, and tile ship in 6–12 weeks.
03 Demolition & protection
2–5 daysDust walls, floor protection, tear-out, and disposal. Hidden conditions surface here, which is why we hold a contingency in every schedule.
04 Framing & structural
3 days–3 weeksWall changes, headers, beams, and subfloor repair. Additions add foundation, framing, and roofing time at this stage.
05 Rough-ins & inspections
1–3 weeksPlumbing, electrical, and HVAC rough-in, then county inspection before anything gets closed up.
06 Insulation & drywall
1–2 weeksInsulation, hang, tape, and three coats of finish with dry time between each. Rushing this is the most visible mistake in a remodel.
07 Finishes
2–5 weeksTile, cabinets, countertop template and install (10–14 days between), flooring, trim, paint, and fixtures.
08 Punch list & final inspection
3–7 daysWalkthrough, touch-ups, final county inspection, and warranty documents handed over.
How to keep your remodel on schedule
- Finalize every selection before demolition — one undecided tile can idle a crew for a week.
- Order cabinets, windows, and custom tile at permit submittal, not after framing.
- Budget a 10–15% time contingency for hidden conditions in homes built before 1980.
- Group change orders into one decision point instead of drip-feeding them.
- Confirm the inspection schedule for your jurisdiction early — review times vary across Columbus, Lancaster, and Logan.
Remodel timeline FAQs
- How long does a home remodel take?
- Most Central Ohio remodels take 6 to 16 weeks of on-site construction, plus 3 to 8 weeks of design, selections, and permitting before crews start. A bathroom runs 3 to 5 weeks on site, a kitchen 6 to 10 weeks, a finished basement 6 to 10 weeks, and a home addition 4 to 7 months.
- How long does a kitchen remodel take in Columbus, Ohio?
- Plan on 6 to 10 weeks of construction once cabinets are on site. Cabinet lead times of 6 to 12 weeks are the single biggest scheduling factor, so we order them before demolition starts.
- How long does a bathroom remodel take?
- A standard hall bath takes 3 to 5 weeks on site. A primary bath with a custom tile shower and layout changes takes 5 to 8 weeks because of added plumbing, electrical, and tile time.
- How long do permits take in Central Ohio?
- Residential permit review typically takes 1 to 4 weeks depending on the jurisdiction. Franklin County and City of Columbus reviews usually run longer than Fairfield or Hocking County, and additions with structural or zoning review can take 4 to 8 weeks.
- What causes remodel delays most often?
- Long-lead materials (cabinets, windows, custom tile), change orders made after work begins, and hidden conditions found at demolition such as failing plumbing, knob-and-tube wiring, or undersized framing.