Central Ohio Timeline Guide

How Long Does a Home Remodel Take in Central Ohio?

Real schedules from projects in Hocking, Fairfield, and Franklin counties — from the first design meeting through final inspection, phase by phase.

Timelines by project type

ProjectOn siteStart to finish
Hall / guest bathroom3–5 weeks8–12 weeks
Primary bath / spa build5–8 weeks11–16 weeks
Kitchen remodel6–10 weeks14–20 weeks
Finished basement6–10 weeks10–16 weeks
Deck or siding1–3 weeks4–8 weeks
Home addition4–7 months6–10 months
Custom natural rock pool8–16 weeks4–7 months

"Start to finish" includes design, selections, permitting, and material lead times — the part most schedules leave out.

The eight phases of a Central Ohio remodel

  1. 01 Design & selections

    2–5 weeks

    Site measure, scope, layout drawings, and every finish selected. Locking selections here is what keeps the build on schedule later.

  2. 02 Permitting & ordering

    1–4 weeks

    Permit submittal to Columbus, Franklin, Fairfield, or Hocking County, and long-lead orders placed — cabinets, windows, and tile ship in 6–12 weeks.

  3. 03 Demolition & protection

    2–5 days

    Dust walls, floor protection, tear-out, and disposal. Hidden conditions surface here, which is why we hold a contingency in every schedule.

  4. 04 Framing & structural

    3 days–3 weeks

    Wall changes, headers, beams, and subfloor repair. Additions add foundation, framing, and roofing time at this stage.

  5. 05 Rough-ins & inspections

    1–3 weeks

    Plumbing, electrical, and HVAC rough-in, then county inspection before anything gets closed up.

  6. 06 Insulation & drywall

    1–2 weeks

    Insulation, hang, tape, and three coats of finish with dry time between each. Rushing this is the most visible mistake in a remodel.

  7. 07 Finishes

    2–5 weeks

    Tile, cabinets, countertop template and install (10–14 days between), flooring, trim, paint, and fixtures.

  8. 08 Punch list & final inspection

    3–7 days

    Walkthrough, touch-ups, final county inspection, and warranty documents handed over.

How to keep your remodel on schedule

  • Finalize every selection before demolition — one undecided tile can idle a crew for a week.
  • Order cabinets, windows, and custom tile at permit submittal, not after framing.
  • Budget a 10–15% time contingency for hidden conditions in homes built before 1980.
  • Group change orders into one decision point instead of drip-feeding them.
  • Confirm the inspection schedule for your jurisdiction early — review times vary across Columbus, Lancaster, and Logan.

Remodel timeline FAQs

How long does a home remodel take?
Most Central Ohio remodels take 6 to 16 weeks of on-site construction, plus 3 to 8 weeks of design, selections, and permitting before crews start. A bathroom runs 3 to 5 weeks on site, a kitchen 6 to 10 weeks, a finished basement 6 to 10 weeks, and a home addition 4 to 7 months.
How long does a kitchen remodel take in Columbus, Ohio?
Plan on 6 to 10 weeks of construction once cabinets are on site. Cabinet lead times of 6 to 12 weeks are the single biggest scheduling factor, so we order them before demolition starts.
How long does a bathroom remodel take?
A standard hall bath takes 3 to 5 weeks on site. A primary bath with a custom tile shower and layout changes takes 5 to 8 weeks because of added plumbing, electrical, and tile time.
How long do permits take in Central Ohio?
Residential permit review typically takes 1 to 4 weeks depending on the jurisdiction. Franklin County and City of Columbus reviews usually run longer than Fairfield or Hocking County, and additions with structural or zoning review can take 4 to 8 weeks.
What causes remodel delays most often?
Long-lead materials (cabinets, windows, custom tile), change orders made after work begins, and hidden conditions found at demolition such as failing plumbing, knob-and-tube wiring, or undersized framing.